Week 13
3 April 2009
Progress
Roof trusses have been installed and gable brickwork completed.
A decision is required on monitoring equipment urgently as internal works will commence at the latest during w/c 13 April 2009.
During week 14 fascia and soffits will be installed. Roof tilers have been booked to lathe and felt roof and tile areas where possible, and solar panels will be fitted.
Project team on site
Andy Berwick - Lovell - Build Manager
Forklift Driver - 1 (shared with another nearby Lovell scheme)
Scaffolders - 2
Joiners – 2
Apprentice Joiner - 1
Bricklayers - 2
Products and Services installed this week
Roof trusses
Roof tiling