Week 2


Report date - 19th January 2009
Completed brickwork to foundations up to DPC (damp proof course).
Installed internal drainage outlets.
Ground floor installed by Tarmac.

Project team on site


Staff and labour on site consist of:
Building Manager 1
Groundworkers 2  
Groundworker Bricklayers 3
Tarmac flooring installers 4
Crane 1

Products and Services installed this week

 
Tarmac Heatsave Plus

 

Photos from Week 2 of Build


See photos of the site.