Week 36
18 September 2009
Progress
The pellet store has been completed. The soakaway from the rainwater harvesting tank has been installed. The base for the cycle store has been concreted. All slabbing has been completed and gravel margins stoned up.
The front and rear gardens have been top soiled and the porous drive installed. Both properties have been cleaned and all surplus materials removed from site.
Landscaping is booked for Monday 28 September. The boiler is to be commissioned following the electric connections being completed. Vinyl flooring is to be fitted along with final paint touch up and clean.
Read more on:
Project team on site
Andy Berwick - Lovell - Build Manager
Joiners – 2
Groundworkers - 2
Plumber - 1